Vellore Village Library: March 6 Update

Construction activities continue at the site of the new library. Glazing installation is nearly completed as insulation, drywalling and taping work continues. Ceiling framing and hangers are well underway and preparation for ceiling work has started. Activities scheduled for the … Continue reading Vellore Village Library: March 6 Update